In recent years, the spread of distributed generation, particularly from renewables, has triggered the introduction of new regulations aimed at visibility and monitoring also for medium-sized plants connected to the distribution grid. More specifically, with its recent Resolution 540/2021/R/eel, Terna requires real-time monitoring of generation plants with power greater than or equal to 1 MW connected at medium voltage (MV).
This measure affects more than 10 GW of installed power across Italy and requires that owners gather data and send it to the distribution company by 31 January 2024.
Act now and book your upgrade to comply with regulation CEI 0-16 and access the incentive
For existing plants, the Authority has set out the issue of a one-off contribution for upgrading costs.
The amount varies based on when you upgrade: the sooner, the greater the incentive available from the CSEA fund for energy and environmental services. Specifically, the amount for existing systems is:
- €10,000 if upgrading work is completed by 31 March 2023;
- €7,500 if upgrading work is completed by 30 June 2023;
- €5,000€ if upgrading work is completed by 30 September 2023;
- €2,500 if upgrading work is completed by 31 January 2024;
There is no incentive available for new plants.

How to upgrade a plant? With a CPC
The key aspect is monitoring of generation plants connected at MV, using a centralised plant controller (CPC).
A CPC is a device for taking direct measurements on the performance of plants, for communication to the distributor through protocol IEC 61850. It is therefore a monitoring system integrated with the production plant on which it is installed, according to the technical specifications set out in Annexes O and T of the CEI 0-16 Standard.
This data-acquisition system has also been developed with a view to future use as a single device for communication with distributors and with Terna for the provision of grid services (UVAM, secondary frequency regulation, etc.).
What happens with existing plants?
Existing plants are identified as those operational prior to 30/11/2022.
For existing plants, the Authority has organised the issue of a one-off contribution for upgrading of plants by January 2024. Those that have not upgraded in the time frame set by the regulations will be considered non-compliant and will risk losing access to incentives that they are currently receiving.
What happens with new plants?
New plants are identified as those becoming operational after 01/12/2022 and they will need to be equipped with a CPC for commissioning. For these plants, regulations set out acquisition of the following information:

General plant information through acquisition of direct measurements using current and voltage transformers

Status of plant and general circuit breakers

Active and reactive power issued by each individual motor
Energy Team’s solution
What can Energy Team offer companies that need to align themselves with the new regulations?
- Supply of unit for acquisition and remote management of measurements at Point Of Delivery;
- Checks and verification of the correct functioning of field equipment;
- Supply of CPC;
- Installation support;
- Support for request for contribution from Authority.
Ongoing support throughout the duration of the contract
- Management of assistance and maintenance;
- Management of communication to the DSO;
- Access to CloE app dedicated to production plants;
- Continuous updating regarding applicable regulations and opportunities to generate income by providing services to the DSO.